UPPCL Private Tube Well Connection Cost Calculator 2026

2026 • Private tube-well connection planning

Estimate the upfront electricity connection cost for a private tube well in Uttar Pradesh. Choose a reference arrangement or enter the charges from your DISCOM estimate. This calculator does not calculate monthly electricity bills, borewell drilling or pump purchase costs.

UPPCL Private Tube Well Connection Cost Calculator 2026

Use the transformer arrangement and line length approved after a site survey. Pump HP alone cannot determine the connection cost.

Reference packages exclude concreting, labour and overheads. Their applicability requires DISCOM confirmation.
Required. Enter 0 only if no new line is required. This is the approved line route, not straight-line distance.
Shows HP × 0.746 in kW for reference; does not select a transformer or sanction load.

Other charges from your demand notice

Leave unknown amounts blank. A blank amount remains unpriced; enter 0 only when confirmed as zero or not applicable.

Enter the actual fee stated for your application.
Enter the total required deposit; no unverified per-HP rate is assumed.
Concreting, labour, overheads, LT work, extra materials or other approved items not already included.
Enter only applicable amounts from the estimate; no automatic blanket GST is added.
Only payments credited toward the same charges included here.

2026 reference charges

Reference arrangementMeteringTransformer sharePackage subtotal
25 kVA, assuming three connections₹6,358₹36,160₹42,518
16 kVA three-phase, one connection₹6,358₹99,670₹1,06,028

UPPCL’s 2026 Cost Data Book Annexures 1 and 1A give these reference packages and a new 11 kV line rate of ₹268 per metre. The quoted transformer and line amounts exclude concreting, labour and overheads. The 25 kVA amount assumes three connections; it is not the cost of a dedicated transformer. Source: UPPCL Cost Data Book annexures.

How the estimate works

The calculator adds the meter charge, applicable transformer share, approved line length multiplied by the selected rate, and the other amounts you enter. It then subtracts the amount already credited toward those items. Unknown fees stay marked “Not entered,” so the result is a priced subtotal rather than a complete connection quote.

Priced subtotal = metering + transformer share + (line metres × line rate) + entered additional charges
Balance for priced items = max(priced subtotal − credited payments, 0)

For the shared 25 kVA reference arrangement with 100 metres of new line, the package and line subtotal is ₹69,318. Processing, security, additional work and any applicable tax remain extra until entered.

What to enter from your DISCOM estimate

  1. Confirm the sanctioned pump load and connection arrangement after the site survey.
  2. Use the approved new 11 kV line length. An existing transformer, different route or different equipment can change the estimate.
  3. Enter processing, security and additional work exactly as priced. Use custom mode if the official estimate differs from the reference package.
  4. Avoid counting the same material, line work or paid fee twice.

Custom mode is useful for existing infrastructure and other surveyed arrangements. It does not assume an existing connection is free. Use the applicable metering, infrastructure and line figures provided by the DISCOM.

Apply for a private tube-well connection

Use the official UPPCL Private Tube Well portal to register, submit an application and follow the application process. The portal provides online payment of the processing fee and estimated cost, application tracking and information about inspection and installation. Check the official demand notice before paying. The electricity helpline is 1912.

For the approved reference document, see the Cost Data Book published by UPERC. Later applicable orders or a revised sanctioned estimate can change payable charges.

Frequently asked questions

Can I calculate connection cost using only pump HP?

No. HP helps describe the load, but the approved line route, transformer arrangement, infrastructure and other charges determine the connection estimate.

Is ₹42,518 the complete tube-well connection cost?

No. It is the meter and transformer-share reference subtotal for the shared arrangement. Line work, omitted construction items and application-related amounts need to be considered separately.

Why does the calculator ask me to enter security and processing charges?

Your applicable demand notice is the best basis for these amounts. The calculator does not fill in older fees or assume they are zero.

Does a monthly agriculture electricity subsidy cover the connection cost?

Do not deduct a recurring bill concession from an upfront connection estimate unless an official sanction explicitly credits it toward those connection charges.

What costs are outside this calculator?

Borewell drilling, pump purchase, private installation costs and recurring electricity bills are outside the calculator. Include only the connection-related amounts you intend to compare with the DISCOM demand.

Planning estimate: This independent calculator is not an official sanction or payment demand. Confirm feasibility, applicable charges and the final payable amount with your DISCOM.